May 13, 2019

Southside Construction Progress Update

Report from Dan Knutson, Project Superintendent for Market & Johnson:

Last week, Market & Johnson finished up 95% of our footings. Leaving only a small section out to access the interior of building with equipment during gang forming and stripping operations. We also were able to pour almost 300’ of wall on the perimeter of the building. We will be finishing up the wall pours mid next week. Wehrs electric connected his ground wire to the footing in the electrical room area. They also provided a sleeve for the wall that we will be running their service through. D&M Mechanical also provided sleeves into wall pour for there laterals running through the wall. We also had a very positive turn out with the groundbreaking today and the kids seemed very happy in the construction process!