Progress continues on our Facilities Expansion Project. Here's an update on construction at the Herrman Elementary site:

Last week, Gerke installed pipes to begin dewatering, the process to remove excess water from retention ponds. They finished mixing the soil underneath where the interior load bearing walls will be set, which allows for better compaction and more stable soil. They have also been working on the bus parking lot.

Market & Johnson continued working on forming foundation walls, and also continued to work on forming footings.