Southside Construction Update - 7/23/19

construction

Last week, Market & Johnson continued to install hollow metal door frames and sealed up the entire addition with temporary enclosures.  They also placed large dehumidifiers thoughout the building. M&J masons finished up the long south wall with the exterior brick and moved inside to begin on the interior block walls. Ledegar Sheet Metal continued to put up large sections of the main HVAC lines. Maurer Roofing sealed up all penetrations in the existing roof for all of the new line sets to the new univents.  Wehrs Electric continued to run conduit and rough in at all the new stud wall locations. Fowler and Hammer continued framing of the new stud walls, and began topping out walls with drywall in a few areas. D&M Mechanical continued the plumbing rough-ins and also continued connecting all plumbing to new toilet areas.