Construction Update - 4/24/20

construction update

4-24-20 Weekly Progress at Herrman Elementary:

M&J Concrete Finishers were on site this week continuing to pour sidewalk. They were able to pour the concrete sidewalk in front of the west main vestibule entrance of unit B and later in the week began preparing the north main bus entrance of unit B. They poured the first portion today in that area as well. M&J Masonry were able to finish laying exterior brick to the last main exterior wall (which was the high southern Gymnasium wall) and at the end of the week they’ve been laying the final brick to miscellaneous smaller areas of the building.

Gerke Excavating was also on site and focused their attention to the northern playground area between the bus parking lot and the school. They were giving the final grade to the ovular areas which will house the playgrounds which also has a largest amount of sidewalk on the entire site.

Winona Heating and Ventilating were also on site applying the waterproof membrane to the canopy areas above the entrances.

Inside the building, the flooring contractors have been continuing to make progress. Comfloors laid the resource room flooring in the 1st floor unit A. Terrazzo Designs continued to install the Terrazzo on the northwest portion of 1st floor unit B and moved to the south east quarter to begin that area.

Professional Painting has continued painting the second floor of unit B and are nearly finished in that area. Fowler & Hammer continued with installing the second floor casework for units A and C. B&B Electric has been continuing with hanging lighting and were also able to hook up the Gymnasium lighting to permanent power-see attached! Cary Specialized Services received the structural framing for the Therapy Swings and were able to install the first two in rooms 21 and 116. Winona Controls focused their efforts again in the Mezzanine and are starting to wrap up the piping intricacies in that area. Zimmerman Plumbing also continued setting the various plumbing fixtures.

H&B Specialized Products came onsite this week and installed the gymnasium and multipurpose room equipment (basketball hoops, etc..)